It is a Constitutional requirement of West Midlands Fire and Rescue Authority (WMFRA) that all expenditure or income, incurred or received, in relation to any contract into which the Service enters, shall be processed in accordance with these Contract Procedure Rules (the Rules) and the Authority’s Financial Regulations. The aim is to ensure a consistent value for money approach to procurement in all areas of activity, in a way that maintains public accountability and complies with all UK Procurement Legislation and minimises the risk of any allegations of fraud or malpractice.
When letting a contract, its monetary value and strategic importance shall determine the appropriate course of action in accordance with the Rules.
All procurements, no matter of value, must follow the objectives of delivering value for money, maximising public benefit, transparency, equal treatment, non-discrimination and acting, and being seen to act, with integrity.
These rules will apply unless they conflict with superseding legislation in which case that legislation will apply.
All procedural matters set out in these rules shall be subject to audit by the Authority’s internal and external auditors.
2. Purpose
The purpose of this policy is to provide the procedure and guidance for awarding contracts on behalf of the Authority.
This policy applies to capital and revenue expenditure. It shall also apply in respect of income, excluding income obtained from external funding, partnerships, sponsorship, or any special funding obtained as part of a bidding process.
3. Responsibility
The procurement process is governed by the Procurement Act 2023 (PA23) and the Procurement Regulations 2024. The policy must be treated the same as legislative rules and is enforceable through Judicial Review.
It is the responsibility of all employees to comply with this policy when procuring goods, services or works.
4. Procedures
4.1 Procurement Planning
4.1.1 Estimated Contract Value and Budget
The Spending Officer must estimate the value of the contract as the maximum payable under the contract, including any amounts already paid. This should include the value of goods, services or works provided, across all Lots, amounts payable if options to extend were taken and amounts payable under the contract representing premiums, fees and commission.
To estimate the value of a Framework (to be awarded by the Authority) the sum of the value of all the contracts that may be awarded under that framework must be used.
Requirements must not be artificially divided to make two or more orders/contracts of a lower value to avoid the requirements to obtain Quotes or Tenders.
Where it is not possible to estimate the contract value then the contract will be treated as having an estimated value of more than the threshold amount for the type of contract.
Further rules on estimating contract values can be found in Schedule 3 of the Procurement Act 2023 or by contacting the Procurement Section.
Financial provision must exist within the approved budget prior to commencement of any procurement activity.
4.1.2 Lots
In the event that the contract value exceeds the Public Procurement threshold, consideration must be given as to whether the contract could reasonably be supplied by more than one contract. The Authority must arrange for the award of the contract or contracts by reference to Lots or provide reasons for not doing so.
A Lot can be a specific geographical area or subject category e.g. goods and training.
The Authority may limit the number of Lots that may be awarded to any one supplier, and in doing so, must provide an objective mechanism for supplier selection in circumstances where a supplier would otherwise exceed the limit.
4.1.3 Thresholds
The procurement process adopted is dependent on the value of the contract. Please refer to the table below to determine the process to be adopted and refer to the appropriate flowchart in appendix 5.2 to obtain guidance.
| Contract Value Including VAT | Contract Value Including VAT | Process | Approval Required |
|---|---|---|---|
| Under £6,000 | Under £5,000 | Obtain 3 quotes if appropriate | If lowest quote, accept. If you wish to accept other than the lowest quote, the reasons and justification must be recorded and retained by Spending Officer. Approval by Budget Holder. |
| £6,000 to £30,000 | £5,000 to £25,000 | Three written quotes | As above |
| £30,000 to £120,000 | £25,000 to £100,000 | Formal Quotations from at least three suppliers processed through Corporate Procurement. Prior to Tender exercise commencing authorisation is required from the Budget Holder to confirm funding is available. | Spending Officer must submit written report to the Corporate Procurement Manager. A copy of the report and approval must be saved with the contract documentation. |
| £120,000 and above | £100,000 and above | Formal Tenders, in accordance with the Procurement Act 2023, following publication of a Tender Notice, except for Call-offs from a Framework Agreement. Processed through Corporate Procurement. | Spending Officer must submit written report to the Assistant Director of Finance and Procurement/Section 151 Officer to obtain approval prior to acceptance or in his or her absence refer to another Brigade Manager. Such approval will be subject to: a) The contract being awarded to the supplier submitting the Most Advantageous Tender b) The value of the contract being within identified funding provisions |
The above amounts include VAT at 20%. If the VAT rate changes it will be the nett (excluding VAT) amounts that will be amended.
4.1.4 Risk Management
A corporate risk assessment must be prepared for all procurements with a potential value over the Public Procurement Threshold or where the failure of the contract will have a significant impact on the core operations of the Authority.
Spending Officers (in conjunction with Corporate Procurement) must:
- maintain a risk register during the contract period;
- undertake appropriate risk assessments for identified risks; and
- ensure contingency measures are in place to comply with the WMFS Business Continuity Plan where appropriate.
4.1.5 TUPE
When any employee either of the Authority or of a service provider may be affected by any transfer arrangement, the Spending Officers must ensure that the Transfer of Undertaking (Protection of Employment) (TUPE) issues are considered and obtain advice from Human Resources and Corporate Procurement before proceeding with inviting Quotations or Tenders.
4.1.6 Data Protection
Where any personal data is shared as part of a contract, applicable data protection legislation (including General Data Protection Regulation (GDPR) and the Data Protection Act 2018) makes it mandatory for data controllers to include specific provisions relating to data protection in their contracts. Corporate Procurement or Information.Governance@wmfs.net should be contacted for details.
4.1.7 Off-payroll working
“Off-payroll working in the public sector” moves the responsibility for deciding if the off-payroll rules for engagements in the public sector transfer from an individual worker’s intermediary to the public authority, agency, or third party paying the intermediary.
The measure makes that public authority, agency, or third party responsible for deducting and paying the associated employment taxes and National Insurance contributions to HM Revenue and Customs (HRMC). Human Resources and Corporate Procurement should be contacted for more information.
4.2 Procurement Design and Timings
4.2.1 Market Engagement
The Authority may conduct market consultations prior to preparing a Tender Specification and should inform the market of their plans. Any decisions made from the engagement should not distort competition or result in a violation of the principles of equal treatment and transparency. A record of any market consultations must be kept with the Tender records.
Where a supplier or a third party related to a supplier has been involved in a pre-market consultation exercise, the Authority must ensure that it takes appropriate measures to ensure that competition is not distorted by the participation of that supplier in the procurement process.
Market engagement should be used for:
- Designing the procurement procedure, conditions of participation or award criteria;
- Assisting with the preparation of the Tender notice and associated Tender documents;
- Identifying suppliers that may be able to supply the goods, services or works required;
- Identifying supply chain risks;
- Help identifying and addressing any Environmental, Social and Governance issues;
- Identifying likely contractual terms; and
- Building capacity among suppliers in relation to the contract being awarded. Before carrying out a market engagement event the Authority must publish a market engagement notice or detail the reasons for not doing so in the Award Notice.
4.2.2 Small and Medium-sized Enterprises
Before inviting Tenders in relation to the award of a below-threshold contract, the Authority must—
(a) have regard to the fact that Small and Medium-sized Enterprises (SMEs) may face particular barriers in competing for a contract, and
(b) consider whether such barriers can be removed or reduced.
4.2.3 Policies
The Authority has a statutory duty to have regard to the National Procurement Policy Statement (NPPS). This means that the Authority must consider whether the procurement can contribute to achieving one or more of the policy objectives stated in the NPPS in a manner that is appropriate, proportionate and relevant; and take steps to address this where possible. This could include, for example, changes to the way the procurement is structured or the process is carried out, the Specification of the goods, services or works to be purchased, or the Award criteria which will determine the Most Advantageous Tender.
The Authority is also required to consider the provisions of the Public Services (Social Value) Act 2012 for any service contracts that are above the Public Procurement Threshold. The main aim of this Act is to ensure that public bodies consider how the services that they are commissioning and procuring might improve the economic, social and environmental well-being of the area in which the services will operate.
Spending Officers must take Social Value into account when awarding a contract in excess of £30,000 (£25,000 excluding VAT) for Supply, Services or Works.
A minimum of 5% of the overall award marks must be allocated to Social Value where Most Advantageous Tender (MAT) is used. It should be noted that a Supplier’s bid cannot be rejected if they decline to offer Social Value unless Social Value is a fundamental part of the Specification, and in such cases, it must be shown as a mandatory requirement.
The Authority will consider the Cabinet Office’s guidance “Tackling Modern Slavery in Government Supply Chains” to identify and manage risks in both new procurement activity and existing contracts.
4.2.4 Procurement Procedures
4.2.4.1 Contracts below £120,000 (£100,000 excluding VAT)
- Up to £6,000 (£5,000 excluding VAT) – obtain three quotes if appropriate. One quote would be considered sufficient where the cost to obtain quotes exceeds the contract value. Corporate Procurement should be contacted for clarification.
- £6,000 to £30,000 (£5,000 to £25,000 excluding VAT) – obtain three written quotes, accept the Most Advantageous Tender, ensuring transparency and equal treatment of all Bidders.
- £30,000 to £120,000 (£25,000 to £99,999 excluding VAT) – Formal Quotations from at least three suppliers processed by Corporate Procurement. Accept the Most Advantageous Tender, ensuring transparency and equal treatment of all Bidders.
If the contract is above £120,000 (£100,000 excluding VAT) one of the procedures below must be followed:
4.2.4.2 Open procedure
- In open procedures, any interested party may submit a Tender in response to a contract notice. Shortlisting of Tenderers is not permitted.
- A minimum of 25 days notice should be given, if all Tender documents are published at the same time and the Tender is advertised electronically. An extra 5 days are required if the tender documents are not published together or an alternative means to electronic advertising is used.
- An Invitation to Tender (ITT) will be produced by Corporate Procurement in conjunction with the appropriate Spending Officer and will be available for all interested suppliers to download from the e-Tendering platform.
- The ITT will include selection and award sections with detailed scoring criteria. All Tenderers passing mandatory selection questions will go through to the award section.
- The timescales for conducting an open Tender process for above Public Procurement thresholds are prescribed within the Procurement Act 2023.
- Completed Tenders must be assessed by the appropriate Spending Officer in conjunction with Corporate Procurement (and other stakeholders as appropriate) against the criteria detailed in the ITT.
4.2.4.3 Competitive Flexible Procedure (CPN)
- This procedure is to be used where there is a requirement to shortlist Tenderers and the contract value is above the Public Procurement Threshold.
- The stages can include:
- Request to Participate/ Conditions of Participation/Excluding Tenderers (Selection) – 25 days
- Limiting Tenderers
- Initial Tender – minimum of 10 days for Tenderers to respond
- Intermediate Assessment
- Limiting Tenderers
- Optional Interaction Round – negotiations (no minimum time requirement)
- Final Tender (no minimum time requirement)
- Assessment
- The Tender documents and stages will be produced by Corporate Procurement in conjunction with the appropriate Spending Officer and will be available for all interested suppliers to download from the e-Tendering platform.
- Completed Tenders must be assessed by the appropriate Spending Officer in conjunction with Corporate Procurement (and other stakeholders as appropriate) against the criteria detailed in the ITT.
4.2.4.4 Further competition or Direct Award through a Framework
- A Framework is an arrangement set up by a third party organisation for the procurement of specific goods, services or works on agreed terms with agreed suppliers, that may be utilised by other organisations as specified in the contractual agreement. Examples of organisations with framework agreements include Crown Commercial Services (CCS), Yorkshire Purchasing Organisation (YPO), etc. Other Fire and Rescue Services and Public Sector bodies may also establish Frameworks It is the responsibility of the Spending Officer and Corporate Procurement to ensure the Framework can be utilised.
- Contracts based on Frameworks may be awarded in one of two ways as follows:
- applying the Specification and terms laid down in the Framework (where such Specification and terms are sufficiently precise to cover the particular call-off) without reopening competition, that is, placing a direct order against a catalogue of goods and/or services.
- where the Specification and terms laid down in the Framework are not precise enough or sufficiently detailed for the particular call-off, by conducting a further competition exercise in accordance with the Framework call-off conditions.
4.2.4.5 Light Touch Procedure
A Light Touch Procedure is for contracts, wholly or mainly for the supply of services, whereby suppliers from outside of the United Kingdom are unlikely to want to compete for contracts for the supply of the services. More details are available from Corporate Procurement.
4.2.4.6 Direct Award
A Direct Award (without competition) can only be made when:
- The contract value is below £6,000 (£5,000 excluding VAT);
- It is for the protection of human, animal or plant life where a Minister of the Crown has provided for it;
- Where no suitable Tenders have been received following a competitive process;
- Where goods, services or works are urgently required and is not the result of an act or omission of the Authority and could not have been foreseen; or
- There are advantageous terms due to a supplier undergoing insolvency proceedings.
- Other circumstances described in Schedule 5 of the Procurement Act 2023.
With the exception of contracts under £6,000 (£5,000 excluding VAT) all Direct Awards must be made by Corporate Procurement, following approval of the Corporate Procurement Manager or Assistant Director of Finance and Procurement/Section 151 Officer, who will provide advice on how to identify the supplier, how to assess the supplier’s ability to meet the requirements, the duration of the contract and contract management.
4.2.4.7 Award to another Public Sector Organisation
Often called Horizontal Awards or Public body to Public body co-operation. Where the contract award would achieve objectives which the authorities have in common, through an arrangement that is solely for the public interest, and the parties perform less than 20% of the services covered by the arrangement on the open market.
4.2.4.8 Use of Approved Suppliers Lists
Approved lists of pre-qualified suppliers should be used where recurrent transactions of a similar type are likely but where such transactions need to be priced individually and cannot easily be aggregated and priced in a single tendering exercise. Approved lists cannot be used for above Public Procurement Threshold contracts.
Spending Officers may draw up, in consultation with Corporate Procurement:
- approved lists of suppliers ready to perform contracts to supply goods, services or works of particular types including without limitation on the basis of agreed contract terms;
- minimum criteria to be accepted on the approved list e.g. appropriate insurance cover, health and safety policy, social value policy, ethical considerations; and
- criteria for the selection of suppliers from the approved list.
No supplier may be entered onto an approved list until there has been an adequate investigation by representatives of Finance, Procurement and any other appropriate sections into the supplier’s financial standing and their technical ability to perform the contract, unless such matters will be investigated each time quotes are invited from that list.
The list and short-listing criteria must be reviewed periodically.
All approved lists shall be maintained in an open, fair and transparent manner.
4.2.5 Specifications
Specifications should refer to performance or functional requirements and include an explanation of the project/minimum requirements, timescales, milestones and critical deadlines. It should also contain any qualifications or accreditations required.
The Specification should not refer to:
- A trademark, trade name, patent, design or type;
- Place of origin, a producer or supplier;
- A design, a particular licencing model or a description of characteristics unless;
- A United Kingdom standard unless;
- The standard adopts an internationally recognised equivalent; or
- There is no internationally recognised equivalent. Where there are no other means by which to communicate the requirement accurately, the Authority must allow “equivalents”, the consideration of which:
- Should include the Authority’s purpose in referring to the standard; and
- May include a requirement for the Supplier to produce a certification, or other evidence, that a standard is satisfied or equivalent. Specifications must not be written to discourage competition regardless of the contract value.
4.3 Procurement Documentation
4.3.1 Transparency Notices
Corporate Procurement will advise on which Notices are required for Covered (above threshold) and Regulated (below threshold) Tenders.
The Notices include, but are not limited to:
- Preliminary Market Engagement Notice – mandatory notice if carrying out pre-market engagement
- Tender Notice – mandatory notice to call for competition for above Public Procurement Threshold procurements
- Contract Award Notice – mandatory notice to inform the market of the intention to award an above Public Procurement Threshold contract and which commences standstill
- Contract Details Notice – mandatory notice to inform the market that an above Public Procurement Threshold contract has been awarded
- Contract Change Notice – mandatory notice to inform the market of a change made to an above Public Procurement Threshold contract
- Contract Termination Notice – mandatory notice to inform the market that the contract has been terminated at the end of term or early
- Below Threshold Tender Notice – notice to call for competition for contracts between £100,000 and threshold, if not using a Framework Agreement
- Payment Compliance Notice – Quarterly notice detailing number of payments made within 30 days In addition to the above the Authority are required to publish details of all payments over £500 (excluding VAT) and contracts awarded over £5,000 (excluding VAT) on its website.
In addition to the above the Authority are required to publish details of all payments over £500 (excluding VAT) and contracts awarded over £5,000 (excluding VAT) on its website.
4.3.2 Associated Tender Documents
Documents to be included with an Invitation to Tender:
- Instruction documents – this is a description of the procedural requirements
- Conditions of Participation (Selection Questionnaire)
- Technical Specification/ Requirements/ Scope of contract
- Assessment Methodology including evaluation criteria
- Copy of draft contract
- Supporting documents as needed to provide sufficient information to prepare a Tender
4.4 Procurement Process
4.4.1 Publication
All notices, documents and information which is published or given in accordance with a provision of the PA 2023 must be published on the Central digital platform.
The “Central digital platform” is the online system established by the Minister for the Cabinet Office.
4.4.2 Administration
All advertisements and contract notices requirements will be placed by Corporate Procurement who will advise on the content and complete the on-line forms.
The process for the receipt of Tenders will be handled by the Central Purchasing Team via the e-tendering platform.
Under no circumstances shall late Tenders, or associated documentation, be accepted.
There is a requirement under the Procurement Act 2023 to retain a record of all material decision making for all above threshold contracts and retained for three years following award of the contract.
4.4.3 Communication
All communication with bidders and suppliers must ensure they are treated equally and without discrimination. The Authority shall act in a transparent and proportionate manner.
A full audit trail will be retained of all communications during a Tender process and retained for three years following award of the contract.
4.4.4 Evaluation and Moderation
Tenders shall be evaluated to assess how requirements will be met and to ensure that consideration has been given to the cost, social value and quality of the solutions offered. Evaluations shall be carried out by the Spending Officer and Corporate Procurement following receipt of completed Tenders.
Evaluations shall be carried out in an open and transparent manner ensuring that all Tenders submitted are treated equally.
All completed Tenders shall be evaluated against the Award criteria as set out in the Invitation to Tender documentation.
Where the examination of a Tender reveals:
- any manifest error or ambiguity (such as an obvious arithmetical error) that can readily be clarified, the supplier shall be given the opportunity to clarify their Tender and confirm this in writing;
- that the offer requires clarification, Corporate Procurement shall contact the supplier to seek clarification via the e-tendering portal; and
- an arithmetical error, subject to the prior approval of the Assistant Director of Finance and Procurement/Section 151 Officer or an officer designated by him or her, the necessary correction shall be notified to the supplier in writing who shall within seven days from receipt of such notice either confirm their Tender in writing as corrected or withdraw it.
4.4.4.1
Contracts below £30,000 (£25,000 excluding VAT) can be awarded based on lowest price or the Most Advantageous Tender (MAT). Where MAT is used the bidders must be informed of the evaluation method at the time of requesting Quotations.
Where the Spending Officer has endeavoured to obtain three Quotations, and where fewer than three were received, the reasons why must be justified to and approved by the Corporate Procurement Manager. In the event of only one Tender being received the Corporate Procurement Manager may request that additional bids are obtained and that the Tender exercise is repeated.
4.4.4.2
Regulated below threshold contracts (between £30,000 (£25,000 excluding VAT) and the Public Procurement Threshold should be awarded to the Most Advantageous Tender (MAT). Evaluation criteria can include requirements or minimum standards relating to suitability, capability, legal status and financial standing. Questions must be relevant to the subject-matter of the procurement and proportionate.
4.4.4.3 Covered procurements (above the Public Procurement Threshold)
During the evaluation of a Covered Procurement Corporate Procurement, referring to the Procurement Act 2023:
- Must exclude Tenderers that cannot meet conditions of participation included in the Tender. These conditions must be a proportionate means of ensuring that the Tenderers have:
- The legal and financial capacity to perform the contract; or
- The technical ability to perform the contract.
- Must exclude Tenderers where:
- A Mandatory Exclusion ground applies to the supplier or an Associated person; and
- the circumstances giving rise to the application of the exclusion ground are continuing or likely to occur again; or
- The tenderer or an Associated person is on the Debarment List by virtue of a Mandatory Exclusion ground.
- May exclude a Tenderer where a Discretionary Exclusion ground applies if the Tenderer cannot provide evidence of self-cleaning.
- Self-cleaning may include replacing a sub-contractor or Associated person or evidence of improvements.
- Must request details of any intention to use sub-contractors and where a sub-contractor is an excluded or excludable supplier, the supplier must be given an opportunity to replace the sub-contractor.
- Must exclude a Tenderer on grounds of improper behaviour, where a Tender has:
- Failed to provide information requested by the Authority,
- Provided information that is incomplete, inaccurate or misleading
- Accessed confidential information, or
- Unduly influencing the contracting authority’s decision-making.
4.4.4.4 The Award Criteria must:
- Be related to the subject-matter of the contract, and can include:
- The goods, services or works to be supplied under the contract, including in respect of any aspect of their production, trading or other stage in their life-cycle
- How or when those goods, services or works are to be supplied
- The qualifications, experience, ability, management or organisation of staff where those factors are likely to make a material difference to the quality of goods, services or works being supplied
- Price, other costs or value for money.
- Be sufficiently clear, measurable and specific
- Not break the rules on technical Specifications; and
- Be a proportionate means of assessing Tenders, having regard to the nature, complexity and cost of the contract.
- Assessment methodology must:
- Describe how Tenders are to be assessed
- If there is more than one criterion, indicate their relative importance; and
- Specify whether failure to meet one or more criteria would disqualify a Tender.
- All evaluation notes must be given to Corporate Procurement to use to produce assessment summaries (see 4.4.4.5) and retained for audit purposes.
- Corporate Procurement should be consulted when evaluation panels and moderation are to be used.
4.4.4.5 Assessment Summaries
Following evaluation of all above Public Procurement Threshold contracts, Bidders must be provided with the following information:
- The assessment methodology set out in full and details of where this is included in the Associated Tender Documents
- The scores and reason for those scores against every award criteria/ strand and
- The reasons why they were not given the score immediately above for every Award criteria / strand.
If unsuccessful, the following must also be provided
- Whether they passed or failed the conditions of participation – and why
- Whether they failed any mandatory questions – and why
- Any other reasons e.g., Failing to meet the technical Specification requirements / equivalence.
4.4.5 Approvals
4.4.5.1 Contract up to £30,000 (£25,000 excluding VAT)
If the Spending Officer wishes to accept other than the lowest quote, the reasons and justification must be recorded and retained by Spending Officer. Approval is provided by the Budget Holder.
4.4.5.2 Contracts between £30,000 and £120,000 (£25,000 and £100,000 excluding VAT)
The Spending Officer must submit a written report to the Corporate Procurement Manager. A copy of the report and approval must be saved with the contract documentation. Approval is provided by the Corporate Procurement Manager.
4.4.5.3 Contracts above £120,000 (£100,000 excluding VAT)
The Spending Officer must submit a written report to the Assistant Director of Finance and Procurement/Section 151 Officer, or in his or her absence refer to another Brigade Manager, to obtain approval prior to acceptance.
Such approval will be subject to:
a) The contract being awarded to the supplier submitting the Most Advantageous Tender and
b) The value of the contract being within identified funding provisions
4.4.5.4 Fire Authority Approval
Prior to commencing a procurement process with a value in excess of £300,000 (£250,000 excluding VAT) a report must be submitted to the Fire Authority detailing the rationale for the forthcoming Tender exercise and must include the proposed route to market and funding provisions. Corporate Procurement is responsible for collating and submitting these reports.
A report may also be submitted to the Fire Authority prior to the award of a contract if such a requirement was indicated by Members following receipt of a pre-tender report.
A retrospective twice yearly Summary Report must be submitted to the Fire Authority for information only for contract awards in excess of £480,000 (£400,000 excluding VAT). This will be produced by Corporate Procurement in conjunction with the Spending Officer.
4.4.5.5 Urgent operational matters
Urgent operational matters that could not have been foreseen by the Authority and CEO/CFO, in consultation with the Chair as set out in the Constitution. A retrospective report must be submitted to the Fire Authority at the next available meeting.
4.4.5.6 Loans, leases and rentals
Loans, leasing or rental arrangements must not be entered into without prior agreement from the Treasurer/Section 151 Officer.
4.4.6 Award
4.4.6.1
Spending Officers may accept Quotations where the total value is less than £30,000 (£25,000 excluding VAT) provided they have been sought and evaluated in accordance with this policy and they have the appropriate authorisation of the Budget Holder. The Spending Officer must arrange for a purchase order to be raised via the Central Purchasing Team.
4.4.6.2
Where the contract value is £30,000 (£25,000 excluding VAT) or above, Corporate Procurement are responsible for the notification to all suppliers simultaneously, of the intention to award the contract to the successful supplier. Corporate Procurement will also be responsible for publishing any relevant Notices.
4.4.6.3 Standstill
The standstill period provides for a short pause between the point when the contract award decision is notified to bidders, and the final contract conclusion, during which time suppliers can challenge the decision.
A voluntary standstill period may be applied before the award of contracts between £120,000 (£100,000 excluding VAT) and the Public Procurement Threshold.
A mandatory standstill period must be applied before the award of contracts above the Public Procurement Threshold, except when awarded through a Framework Agreement, when a voluntary standstill may be used.
The standstill period of eight working days will commence on the day the Contract Award Notice is published.
Under no circumstances should a Contract be entered into until the end of the Standstill Period, and no challenges have been received.
4.4.6.4 Purchase Orders
Following award of any contract the Spending Officer must arrange for a purchase order to be raised as soon as possible. For higher value/high risk contracts the contract must be signed by all parties prior to a purchase order being raised.
4.4.6.5 Contract Details Notice
A Contract Details Notice is required to be published for all above Threshold contract awards. Where the contract value exceeds £5,000,000 (c £4,165,000 excluding VAT) a redacted copy of the contract is also required to be published, along with a minimum of three KPIs.
4.4.6.6 Procurement termination
If it is determined that the contract for the goods, services or works is no longer required and therefore the procurement exercise needs to be terminated, the Spending Officer shall forward all associated documentation to Corporate Procurement with an explanation of why the exercise needs to be terminated. In the event that the procurement exercise is terminated Corporate Procurement will publish the relevant Notice.
4.5 Contract Execution and Management
4.5.1 Execution
Contract execution is an event in which all appropriate parties sign the contract, and the contract becomes legally binding. Corporate Procurement will arrange the signing of contracts through an electronic signing platform.
4.5.1.1
Where the contract value is between £30,000 and £120,000 (£25,000 and £100,000 excluding VAT) a written contract should be in place and signed by the Corporate Procurement Manager for the Authority.
4.5.1.2
Where the contract value is between £120,000 and £300,000 (£100,000 and £250,000 excluding VAT) a written contract must be in place and signed by the Assistant Directorof Finance and Procurement/Section 151 Officer.
4.5.1.3
Where the contract value is above £300,000 (£250,000 excluding VAT) the contract will be assessed by Corporate Procurement as to the nature and potential risk. Where deemed appropriate, and approved by the Assistant Director of Finance and Procurement/Section 151 Officer the contract will be executed as a Deed (signed under seal and witnessed by the Clerk to the Authority). Where not executed as a Deed 4.5.1.2 will apply.
4.5.2 Contract Management
Ongoing contract management arrangements should be considered upfront at the pre-tender stage and must be discussed with Corporate Procurement. Contract management should also be incorporated into the final contract.
Things to consider are:
- Type of communication required with the supplier e.g. e-mail, conference call, face to face meeting, Teams, etc
- Frequency of contact/meetings
- Location of meetings
- Who should attend the meetings from all parties
- What management information the suppliers are to provide and how often
- Monitoring delivery of Social Value offered
- What Service Level Agreements (SLA’s) are required and/or service credit arrangements if they aren’t met
- What Key Performance Indicators (KPI’s) are required
The prime responsibility is with the Spending Officer to manage the contract following award.
Once a contract has been awarded it is the Spending Officer’s responsibility to ensure that the chosen supplier(s) provides the service that was expected and agreed following the Quotation/Tender process.
Corporate Procurement should be involved in any discussions regarding commercial, contractual or recurring issues but it is expected that Spending Officers will be responsible for any day to day technical or operational issues.
4.5.3 Key Performance Indicators (KPIs)
Where a supplier’s performance can be assessed by reference to Key Performance Indicators (KPIs) KPIs they must be included in the contract.
Before entering into a contract with an estimated value of more than £5,000,000 (c £4,165,000 excluding VAT) the Authority must set at least three KPIs in respect of the contract.
The Authority must publish an annual Contracts Performance Notice which reports on a supplier’s performance against these KPIS.
The above does not apply to Framework Agreements but does apply to call-off contracts made under a Framework Agreement.
4.5.4 Modification and Extensions
A contract modification may refer to an extension of the contract period or to changes/amendments to the contract Specification or service provision.
The Authority may modify a contract if the modification is not a substantial modification.
A substantial modification is a modification that would:
- increase or decrease the term of the contract by more than 10 per cent of the maximum term provided for on award,
- materially change the scope of the contract, or
- materially change the economic balance of the contract in favour of the supplier.
Modifications may be undertaken to existing contracts awarded competitively provided that:
a) where the modification, irrespective of value has been provided for in the initial procurement documents in precise, clear and unequivocal review clauses. Such clauses must specify the scope and nature of possible modifications or options as well as the conditions under which they may be used. In addition, the clauses must not alter the overall nature of the contract.
b) where the modification has been brought about by circumstances that could not have been foreseen and the modification does not alter the overall nature of the contract, and any increase must not exceed 50% of the contract price.
c) where the modification has been brought about by circumstances that are for the protection of human, animal or plant life where a Minister of the Crown has provided for it.
d) where a known risk has materialised which is not the result of any act or omission of the Authority or the supplier. The modification must go no further than to remedy the fact. The modification must not increase the estimated value of the contract by more than 50%.
A known risk, because of its nature, could not be addressed in the contract as awarded and must have been identified in the Tender or transparency notice for award of the contract.
e) where additional works, services or supplies have become necessary and were not included in the original procurement, but a change of contractor is not possible for economic or technical reasons or because it would cause significant inconvenience or duplication of costs. The modification must not exceed 50% of the contract price.
f) where a new contractor replaces the previous contractor as a consequence of an unequivocal review clause or the succession of the initial contractor due to a merger, company acquisition etc provided that the new contractor meets the qualitative criteria established during the procurement.
g) the modification is low value and below the threshold (for the type of contract) and is below 10% for supplies and services and 15% for works of the original contract price as long as the modification does not alter the overall nature of the contract.
b) and c) above cannot be used for contracts awarded under Public Contract Regulations 2015 (PCR2015).
Contracts awarded under Public Contract Regulations 2015 (PCR2015) and still “live” beyond 28 October 2024 remain subject to the amendment rules stated in that legislation. PCR2015 has different rules to the Procurement Act 2023 on the timing of the contract value to be used for modifications, therefore Corporate Procurement must be consulted prior to discussing modifications with suppliers.
For modifications between £6,000 and £120,000 (£5,000 and £100,000 excluding VAT) and where the total revised contract value does not exceed £120,000 (£100,000 excluding VAT), a written report should be compiled and submitted to the Corporate Procurement Manager for approval.
For modifications to contracts where the revised contract value exceeds £120,000 (£100,000 excluding VAT) a written report should be compiled detailing the required extension or variation and submitted to the Assistant Director of Finance and Procurement/Section 151 Officer for approval or another Brigade Manager in his or her absence.
Where the revised contract value (following modification) exceeds £480,000 (£400,000 excluding VAT), a retrospective report must be submitted to the Fire Authority for their information.
Contract modifications should not be agreed with suppliers until approval has been obtained.
Contract change notices must be published, when the revised contract value exceeds the threshold for public contracts, within 30 days.
4.5.5 Payment Terms
All contracts will include expressed 30-day payment terms between the Authority and supplier.
These terms are also expressed into public sub-contracts.
Payment notices must be published detailing compliance by the Authority with this requirement.
The Authority must publish details of payments which are over £30,000 (as per the Transparency Code).
4.5.6 Contract Termination
Corporate Procurement will be responsible for publishing a Contract Termination Notice within 30 days of the end of an above threshold contract. Notices are required to be published at the end of the contract term or on early termination.
4.5.7 Record Keeping
The Authority must keep such records as the Authority considers sufficient to explain a material decision made for the purpose of awarding or entering into a public contract:
- To publish or provide a notice, document or other information in relation to the decision, or
- To make the decision
- Any communication between the Authority and a supplier that is made in relation to the award or entry into of a public contract, and
- Before the contract is entered into.
These records are to be kept until:
- A notice is published that there will not be an award
- Three years post contract award
4.6 Other Considerations
4.6.1 Conflict of Interest
The Authority must take all reasonable steps to identify, and keep under review, any conflicts of interest. The concept of conflicts of interest shall cover any situation where relevant staff members have, directly or indirectly, a financial, economic or other personal interest which might be perceived to compromise their impartiality and independence in the context of the procurement procedure.
The Authority must take reasonable steps to ensure a Conflict of interest does not put a supplier at an unfair advantage or disadvantage in a procurement.
Where a supplier has an advantage that cannot be avoided, or the supplier will not take steps necessary to ensure they do not have an unfair advantage then the Authority must exclude the supplier from participating in the Tendering process.
A Conflict of interest summary must be completed for all contracts above £120,000 (£100,000 excluding VAT) and reviewed periodically.
Any employee of WMFS with a pecuniary or other interest in any contract let by the Authority must, whether or not they have been directly involved in the award of such a contract, submit a report to the Human Resources detailing the nature of their interest.
Human Resources will maintain a register of pecuniary interests for inspection by auditors and will verify annually that any declared interests are still current.
Employees should not let personal or private interests affect their judgement of the public interest. Members of the Authority and employees should treat these non-pecuniary interests on the same basis as the law requires them to treat pecuniary interests. Members’ interests shall be registered by the Clerk to the Authority.
Members or employees needing to declare interests should refer to the Anti-Fraud, Corruption and Bribery Policy.
Employees should ensure that hospitality given or received in connection with their appropriate duties can always be justified in the public interest. Similarly, gifts should not be accepted, the only exception being items of a very minor complimentary or token nature which could in no way be construed as offering financial or other material inducement (Anti-Fraud Corruption and Bribery Policy for further guidance).
4.6.2 Special Exemptions
Spending Officers wishing to enter into a contract where there is deemed to be a ‘special exemption’ must obtain prior approval from the Corporate Procurement Manager for contracts valued under £120,000 (£100,000 excluding VAT) and the Assistant Director of Finance and Procurement/Section 151 Officer for contracts valued at £120,000 (£100,000 excluding VAT) and over, identifying the reason for the exemption and that part of the Policy to which it applies.
This provision does not apply to Facilities Management for emergency building works of less than £9,000 (£7,500 excluding VAT) in value.
If the Assistant Director of Finance and Procurement/Section 151 Officer was involved in the initial decision-making process then approval for the exemption must be sought from another Brigade Manager.
Examples of circumstances in which an exemption might be appropriate are as follows:
a) the goods or materials are purchased or sold at auction, public fairs or markets
b) the provision of goods, services or works is obtainable only from one supplier and no satisfactory alternative is available
c) there are fewer than three suppliers known to be in the market for particular goods, services or works, (in such cases, Tenders shall be invited from such lesser number of suppliers)
d) the prices of the goods, services or works are wholly controlled by trade organisations or government order and no reasonable satisfactory alternative is available
e) Tenders have or will be invited on behalf of any consortium, collaboration or similar body in which the Authority is participating, in accordance with any method adopted by such a body
f) the goods or services are deemed expedient for Service requirements
g) where the goods, services or works are so urgently required as not to permit the Invitation of Tenders and the nature of the urgency was unforeseen. In such cases, the prior approval of the Assistant Director of Finance and Procurement/Section 151 Officer, or another Brigade Manager in their absence, must be obtained.
Separate special exemption rules apply where the value exceeds the Public Procurement Threshold and are very limited. Advice must be sought from the Corporate Procurement Manager in this instance. Under no circumstances does the Authority have the power to waive its obligations under law.
Where a contract or agreement is entered into under paragraph 4.6.2 (above) and its value exceeds £480,000 (£400,000 excluding VAT), a retrospective report must be submitted to the next available Fire Authority Meeting. Corporate Procurement is responsible for the compilation and submission of these reports.
4.6.3 Bonds and Parent Company Guarantees
The Spending Officer must consult the Assistant Director of Finance and Procurement/Section 151 Officer about whether a parent company guarantee is necessary when a supplier is a subsidiary of a parent company and:
- the award is based on evaluation of the parent company and there is some concern about the financial stability of the supplier.
- The Spending Officer must consult the Assistant Director of Finance and Procurement/Section 151 Officer about whether a bond is needed where:
- the total contract value exceeds £500,000; and
- it is proposed to make staged or other payments in advance of receiving the whole of the subject matter of the contract and there is concern about the financial stability of the supplier.
4.6.4 Purchasing cards
The authority operates a purchase card facility; these are available, with the approval of the Assistant Director of Finance and Procurement/Section 151 Officer.
- Purchase cards are to be used for low value; incidental, retail spend where there is no competition.
- Purchase cards MUST NOT be used to bypass corporate contracts without the express permission of the Corporate Procurement Manager.
The principle of disaggregation applies to spend on purchase cards both in relation to the individual and the Authority as a whole.
4.6.5 Retention of documents
Financial documents are required to be retained for six years from the end of the financial year they relate to. Documents include those that detail:
- all money spent by the Authority, for example receipts, petty cash books, orders and delivery notes
- all money received by the Authority, for example invoices, contracts, sales books and till rolls
- any other relevant documents, for example bank statements, credit card statements and correspondence
Unsuccessful Tender submissions may be disposed of 12 months after contract award.
Contract documentation should be retained for a period of six years after expiry of the contract unless the contract is awarded as a Deed (with the Authority’s seal attached).
Contracts executed under seal must be retained for a period of 12 years after contract expiry.
Paper copies of contracts above £120,000 (£100,000 excluding VAT) are to be filed by Service Support Administration.
4.6.6 Disposal
Assets that are no longer required should be disposed of to avoid unnecessary maintenance, risk and insurance costs. Before disposal the Budget Holder must make a judgement as to whether the asset can be reused elsewhere in the Service. Assets that are no longer functional, are not fit for purpose or are beyond economical repair must be disposed of.
Disposal options (in order of consideration)
- Reuse within the Service
- Sell; contact the Central Purchasing Team or the Warehouse & Distribution Section to discuss options. A minimum of two bids should be obtained for all assets with a value in excess of £6,000 (£5,000 excluding VAT).
- Donate to charity.
a) The majority of donations will be directed via Fire Aid and their partner organisations. Requests for redundant equipment must be made by an organisation which is undertaking the role of local government. Further information on how to do this can be obtained from Corporate Procurement.
b) Condemned uniform should be placed in the Firefighter Charity boxes. All Service branding must be removed or cut through before putting in the charity box.
4. Scrap
Methods 2, 3 and 4 required the approval of the Corporate Procurement Manager prior to disposal.
Sale proceeds should be refunded back into the budget that the asset was originally purchased from. All sales must be reported to Revenues to enable an invoice to be raised.
4.6.7 Overseas Aid
It is the policy of the Authority to:
Provide humanitarian aid to communities in countries outside the UK (where such requests are made by the governments of countries experiencing a recognised natural disaster, or national catastrophe) which will improve the lives of those in need or increase their firefighting capabilities.
Dispose of outdated firefighting equipment to countries overseas where there are insufficient funds to provide such equipment for themselves, which will benefit their community or fire personnel.
All requests for the provision of aid to a country outside of the United Kingdom should be submitted in writing to the appropriate section head.
The section head will forward the request to the relevant Brigade Manager for consideration and approval. Please Note: Costs of transportation will not be met by the Authority, and insurance is required to be arranged in accordance with the instructions in Management of Occupational Road Risk (MORR) .
Any personnel making such a request will have to make sure that the proposal falls within the Local Government (Overseas Assistance) Act 1993.
Appendices
Appendix 1 – Procurement Policy Definitions
| An Associated person | A person that the supplier is relying on in order to satisfy the conditions of participation, but not a person who is to act as guarantor |
| Associated tender documents | Documents that supplement the Tender notice and provide duplicate information or further detail about the procurement and could include things like the Specification, evaluation methodology, terms and conditions etc |
| The Authority | West Midlands Fire and Rescue Authority |
| Award Criteria | Criteria to assess tenders against for the purpose of awarding a public contract to the Most Advantageous Tender (MAT) |
| Below threshold contract | Not a covered procurement, but may be subject to obligations in Part 6 of the Procurement Act |
| Budget Holder | The person or persons authorised to incur expenditure in accordance with the estimates that make up a budget. |
| Central digital platform | A central “online system” for the publication of notices, documents and other information in relation to the Procurement Act |
| Competitive flexible procedure | A flexible tendering procedure to be used when shortlisting or multiple stages are required |
| Conflict Assessment | An assessment that includes details of— (a) conflicts or potential conflicts of interest identified in accordance with section 81 (duty to identify), and (b) any steps the Contracting Authority has taken or will take for the purposes of section 82 (duty to mitigate). |
| Conflict of Interest | A personal, professional or financial interest which may be direct or indirect |
| Contract | An agreement between two or more competent parties for the provision of goods, services or works. Some contracts are required to be in writing in order to be enforced. |
| Contracting Authority | Means a person that is— – wholly or mainly funded out of public funds, or – subject to public authority oversight, – and does not operate on a commercial basis |
| Convertible contract | Contracts that increase to become above threshold in total value. |
| Corporate Procurement | The central procurement section charged with providing strategic direction and advice to secure value for money on all procurement matters. The Corporate Procurement Manager is in charge of this section under the Assistant Director of Finance and Procurement/Section 151 Officer. |
| Covered procurement | Above threshold public contracts which are subject to the general rules of the Procurement Act |
| Debarment List | A published list of excluded (where a Mandatory Exclusion ground applies) or excludable (where a Discretionary Exclusion ground applies) suppliers. |
| Direct Award | A non-competitive process governed by s.41-44 and schedule 5 of the Procurement Act 2023 |
| Discretionary Exclusion | See Excludable supplier below |
| Dynamic market | Are a list of qualified suppliers who are eligible to participate in future procurements. They can be set up for a wide range of goods, services and works covered under the Procurement Act, which would benefit emerging and niche markets rather than commonly used goods and services. There are no restrictions on the term or the number of suppliers that can be part of the dynamic market. |
| Estimated contract value | Total estimated value of a contract including all available options (e.g. extensions) including VAT |
| Excludable supplier | Where a Discretionary Exclusion ground applies contracting authorities have the discretion on whether to exclude an Excludable Supplier from a procurement procedure or contract award |
| Excluded supplier | Where a Mandatory Exclusion ground applies contracting authorities have to exclude the supplier from a procurement procedure or contract award |
| Framework | A contract with suppliers that provides for the award of future contracts (known as call-off contracts). The framework must set out certain information relating to the call-off contracts, such as the price payable under call-off contracts or the mechanism for determining this |
| Invitation to Tender (ITT) | Complete document set that is published to invite tenders |
| Judicial Review | A type of court proceeding that reviews the lawfulness of a decision or action made by a public body. |
| Key Performance Indicator | A “key performance indicator” is a factor or measure against which a supplier’s performance of a contract can be assessed during the life-cycle of the contract. |
| Lots | The parts into which a procurement of supplies, works or services might be divided. |
| Mandatory Exclusion | See Excluded Suppliers above |
| Most Advantageous Tender (MAT) | The tender that satisfies the Authority’s requirements, and best satisfies the award criteria. |
| National Procurement Policy Statement (NPPS) | A statement setting out the Government’s strategic priorities in relation to procurement |
| Preliminary Market Engagement | Engagement with suppliers before a tender notice is published |
| Procurement Act 2023 (PA23) | The Act of Parliament that specifies Public Sector procurement rules |
| Procurement Regulations 2024 | The companion legislation and schedules that add further detail to the Procurement Act 2023. |
| Public Procurement Threshold (Threshold) | The contract value at which the Procurement Regulations apply. These thresholds are provided for in the Regulations and derive from the WTO Agreement on Government Procurement (GPA) |
| Quotation | A Quotation is a response to a Request for a Quotation (RFQ), which is used to identify the best supplier who can meet the requirements and off the best value for money. Quotations are used for contracts with values below £100,000 |
| Regulated Below Threshold Contract (Below Threshold) | A contract of £30,000 (inc VAT) and below the Public Procurement Threshold |
| The Service | West Midlands Fire Service |
| Small Medium Enterprise (SME) | Suppliers that have fewer than 250 staff and have a turnover of an amount less than or equal to £44 million, or a balance sheet total of an amount less than or equal to £38 million. |
| Social Value | A measure of outcomes and benefits from any activity that tackles social problems, improves people’s lives, communities or the environment. |
| Specification | A detailed description of the characteristics of a commodity or service required or desired. |
| Spending Officer | An employee of WMFS who has a requirement for goods, services or works to be purchased from a third party in order to support the activities of West Midlands Fire Service. |
| Tender | A Tender is a response to the invitation to Tender, which is used to identify the best supplier who can meet the requirements and off the best value for money. Tenders are used for contracts with values above £100,000 |
| Transparency Notices | A notice, document or information which is published or given in accordance with a provision of the PA 2023 must published or given by publishing it on the central digital platform. |
Appendix 2 – Flowcharts
Process: Below £25,000 excluding VAT
- Prepare specification and check budget (Action by Spending Officer)
- Request 3 quotes (Action by Spending Officer)
- Evaluate quotes based on lowest price (Action by Spending Officer)
- If lowest quote, accept. If you wish to accept other than the lowest quote, the reasons must be retained by the Spending Officer. Approval by Budget Holder. (Action by Spending Officer)
- Raise requisition in Oracle Procurement (Action by Spending Officer)
- Goods delivered (Action by Spending Officer)
- Good receipt in Oracle (Action by Spending Officer)
- Invoice received and checked against Purchase order and Goods Receipting (Action by Procurement, Finance or Oracle)
- Supplier paid (Action by Procurement, Finance or Oracle)
Process: £25,000 to £100,000 excluding VAT
Estimated time from start to award of contract: between 1 week and 3 months. Timescales will vary depending on the complexity of the procurement and number of bidders.
- Prepare specification and check budget (Action by Spending Officer)
- Consider social value, IR35, Conflict Assessments etc (Action by Spending Officer with Procurement)
- Identify award criteria (Action by Spending Officer with Procurement)
- Corporate Procurement to request quotes through e-tender portal (Action by Procurement, Finance or Oracle)
- Evaluate quoted based on agreed award criteria (Action by Spending Officer with Procurement)
- Approval by the Corporate Procurement Manager (Action by Procurement, Finance or Oracle)
- Raise requisition/order in Oracle Procurement (Action by Spending Officer)
- Goodes/Service/Works delivered (Action by Spending Officer)
- Goods receipt in Oracle (Action by Spending Officer)
- Invoice received and checked against Purchase order and Goods Receipting. Supplier paid. (Action by Procurement, Finance or Oracle)
- Where required, regular contract monitoring throughout the life or the contract (Action by Spending Officer with Procurement)
- All decision making recorded and retained by Corporate Procurement (Action by Procurement, Finance or Oracle)
Process: above £100,000 excluding VAT
Estimated time from start to award of contract: up to 9 months. Timescales will vary depending on the complexity of the procurement and number of bidders.
- Identify the requirement (Action by Spending Officer)
- Preliminary market engagement (Procurement to publish notice) (Actions by Spending Officer with Procurement and Actions by Procurement, Finance or Oracle)
- Consider social value, IR35, Conflict Assessments and outcomes from market engagement (Action by Spending Officer with Procurement)
- If above £250,000 Fire Authority approval is required before commencing tender (Action by Procurement, Finance or Oracle)
- Prepare the specification and confirm budget (Action by Spending Officer)
- Identify award criteria (Action by Spending Officer with Procurement)
- Complete ITT documents (Action by Spending Officer with Procurement)
- Legal service to review documentation (Action by Procurement, Finance or Oracle)
- Corporate Procurement to publish tender notice and ITT through e-tender portal (Action by Procurement, Finance or Oracle)
- Tenders received and evaluated based on published criteria (Action by Spending Officer with Procurement)
- Approval by the Assistant Director of Finance and Procurement/Section 151 Officer (Action by Procurement, Finance or Oracle)
- Procurement publish contract award notice (Action by Procurement, Finance or Oracle)
- 8 day standstill period (if included) (Action by Procurement, Finance or Oracle)
- Procurement publish contract details notice (Action by Procurement, Finance or Oracle)
- Supplier and Authority sign the contract (Action by Procurement, Finance or Oracle)
- If above £250,000 Procurement to add to the Fire Authority Award report (Action by Procurement, Finance or Oracle)
- Raise requisition/order in Oracle Procurement (Action by Spending Officer)
- Goods/Service/Works delivered. Spending officer to good receipt (if required) (Action by Spending Officer)
- Invoice received and checked against Purchase order and Goods Receipting & supplier paid (Action by Procurement, Finance or Oracle)
- All decision making recorded and retained by Corporate Procurement (Action by Procurement, Finance or Oracle)
- Regular contract monitoring throughout the life of the contract (Action by Spending Officer with Procurement)
- Publish contract performance and payment notices (Action by Procurement, Finance or Oracle)
- Procurement publish contract termination notice (Action by Procurement, Finance or Oracle)
Appendix 3 – Legislation
Procurement Act 2023 – Legislation
The Procurement Regulations 2024
Public Services (Social Value) Act 2012 – Legislation
Modern Slavery Act 2015 – Legislation
Appendix 4 – Transparency Notes
| Notice | Details | Section of the Procurement Act 2023 | Section of the Contract Regulations 2024 |
| Pipeline Notice | Where organisational procurement spend is above £100m there is a requirement to publish 12-month forward plan of procurements £2m+ | 93 | 15 |
| Planned Procurement Notice | Publish a qualifying planned procurement notice to reduce Tender timescales | 15 | 16 |
| Preliminary Market Engagement Notice | Publish where pre-market engagement is planned or has taken place (or explain why not, in Tender notice) | 17 | 17 |
| Tender Notice | A notice to invite Tenders | 21 | 18 to 22 |
| Procurement Termination Notice | Publish if, following a Tender or transparency notice, the procurement ends without a contract award | 55 | 37 |
| Contract Award Notice | Notice of intention to award a contract | 50 | 27 |
| Contract Details Notice | Notice detailing the award of a contract. If the contract value is £5m+ a copy of the contract must be published as well | 53 | 32 to 36 |
| Payments Compliance Notice | A notice detailing the percentage of payments made within the 30 days terms | 69 | 38 |
| Contract Payments Notice | Publish where one or more individual contract payment of £30k+ is made under a public contract | 70 | n/a |
| Contract Performance Notice | Publish annual KPI data (contracts £5m+), and/or as required to report breach of contract / poor performance. | 71 | 39 |
| Contract Change Notice | Publish when making a contract modification | 75 | 40 |
| Contract Termination Notice | Publish notice to confirm the end of a contract e.g. end of contract term, early termination etc | 80 | 41 |
| Transparency Notice | A notice that the Authority intends to award a contract directly, without competition | 44 | 26 |
| Dynamic Market Notice | Publish to advertise, establish, change or terminate a dynamic market | 39 | 25 |
| Below Threshold Notice | A notice setting out that the Authority intends to award a below procurement threshold contract | 87 | 24 |